The Generalitat is promoting a direct connection from the Júcar-Vinalopó transfer to the Los Suizos reservoir, which supplies over 1,000 irrigators from Albatera and Hondón de los Frailes. The project will avoid pumping and reduce electricity consumption.
According to Alicante Plaza, the Valencian Generalitat is preparing an investment of 7.7 million euros to connect the Júcar-Vinalopó transfer with the reservoir of the SAT Virgen del Rosario, known as Los Suizos. The reservoir serves 1,049 irrigators from Albatera and Hondón de los Frailes, covering an agricultural area of 914 hectares.
The project consists of a pipeline of about two kilometres from section VII of the transfer to the reservoir. It will take advantage of the natural pressure of the water, meaning pumping will not be necessary, thus reducing the electricity costs currently borne by farmers.
The connection will also prevent the water from the Júcar from mixing with that from the wells in the Sierra de Crevillente. As explained by the Ministry of Agriculture, this mixing promotes the proliferation of algae that clog filters and networks, necessitating supply cuts for cleaning.
“The direct connection will allow us to take advantage of the natural pressure of the Júcar water to bring it to the reservoir without the need for pumping, which will result in energy savings for the irrigators and improve the efficiency of the system,” explained the Minister of Agriculture, Miguel Barrachina.
Currently, water reaches the Los Suizos gallery, where it loses pressure before being pumped to the reservoir. This situation prevents irrigators from receiving the full volume allocated to them. During 2025, the SAT received 4.1 hectometres cubic, compared to the 5.27 hectometres cubic planned in the exploitation plan for 2026-2027.
Regarding the procedures, the project received a favourable report from Supervision on November 12 and is now in the phase of budget update and environmental consultation. The next step will be to commission the public company Tragsa, which would carry out the works. There is currently no start date.
The Valencian government also maintains 30 million euros for the first two phases of modernisation of the left bank of the transfer, affecting Monóvar, Novelda, Monforte del Cid, and Agost. Barrachina also called for the repair of the San Diego reservoir in Villena to regulate the flows of the system.
“Farmers need to have guaranteed access to the water that corresponds to them and to have infrastructure that allows them to take advantage of it at the lowest possible cost,” noted the regional official.