ACUAMED will build the desalination plants in Blanes and Cubelles with a joint investment of €513 million. The two plants will reduce Catalonia's dependence on rainfall.
As reported by retema.es, the Spanish Government and the Catalan Government have already approved the agreement that will allow the tendering of the expansion of the Tordera desalination plant and the new Foix plant. With a joint investment of €513 million, both facilities aim to reduce the dependence of the Catalan system on precipitation.
The works will be carried out by the state public company ACUAMED, with the participation of the Ter-Llobregat Water Supply Agency (ATL). The Generalitat's strategy aims for 70% of Catalonia's water resources to come from unconventional sources, so that only 30% directly depends on rainfall.
In Blanes (Girona), the Tordera expansion will add 60 hm³ annually to the 20 hm³ currently produced by the facility, reaching a total of 80 hm³. The basic project has already received final approval, and the tendering for the construction project and works will take place in the first quarter of 2027. The plant is expected to be operational by March 2031, with an investment of €290 million.
In Cubelles (Barcelona), the new Foix desalination plant will start with a capacity of 20 hm³ annually, expandable to 30 hm³ according to future needs. The final approval of the basic project will arrive in December 2026, and the tendering of the works will occur in April 2027. The plant, with an investment of €223 million, is expected to be in service by June 2031.
Both plants will strengthen the Ter-Llobregat system, which supplies approximately 5.5 million people. They will provide resources independent of stored reserves, something the Catalan Government considers crucial for supply in the southern part of the metropolitan area.
As the works could not be executed within the timeframes required by European credits, a new financing scheme has been designed. It will combine state resources with money obtained from financial markets. According to the Generalitat, this formula guarantees the financial viability of both projects and allows progress towards tendering in 2027.
Both projects are part of a broader programme that includes water regeneration, the utilisation of resources from the Besòs, improvements to water treatment plants, and the efficiency of distribution networks. The goal is to strengthen water security in the face of future droughts, such as the one recorded between 2021 and 2024, which the Catalan Government describes as the longest and most intense in the last two centuries. The next milestone is the approval of the basic project for the Foix in December 2026.