The local government of L'Hospitalet has officially approved a significant renovation project for the Collblanc market, set to begin soon. With a budget nearing €2 million, this initiative aims to modernize one of Barcelona's largest markets despite ongoing protests from some vendors.
The historic Collblanc market in L’Hospitalet de Llobregat is poised for a transformative renovation after the local government granted final approval for the project. This decision comes with a budget of €1.93 million and aims to revitalize one of the most significant markets in the Barcelona area. The first phase is expected to commence shortly, pending the publication of bidding details.
The project has faced considerable opposition from external vendors who have raised concerns about their future operations during and after the renovations. Despite these objections, all appeals submitted by the Association of External Vendors were denied by city officials.
The renovation will unfold in three major phases. Initially, four interior shops will be relocated from an underutilized corner to a busier area within the market, allowing for an open space where current stalls are situated. Subsequently, external vendors will gradually move indoors as their current stalls are dismantled and replaced with new structures that comply with safety standards.
This extensive remodeling effort is not just about aesthetics; it addresses critical issues such as leaks and asbestos presence that have plagued the market for years. Built in 1932, under the design of municipal architect Ramon Puig i Gairalt, Collblanc has long served as a vital community hub located near Barcelona and close to Camp Nou.
“We do not want to move inside. We will die if we go inside,” said Pilar Andrés, president of the external vendors’ association, expressing fears that such changes could jeopardize their livelihoods.
The local government has expressed its commitment to minimizing disruptions for affected vendors during construction. According to council member José Antonio Alcaide, plans include installing temporary stalls—36 in total—once interior spaces become available post-relocation.
This phased approach aims to ensure continuity for vendors while addressing necessary upgrades within the market structure. However, many vendors remain skeptical about whether these measures will adequately protect their interests throughout this lengthy process.
The timeline for completing all phases remains uncertain but could extend over several years due to the complexity involved in relocating stalls and ensuring compliance with modern safety regulations.
“This will take longer but reduce provisionality,” Alcaide noted regarding the planned segmented execution strategy.
As discussions continue between city officials and vendor representatives, there remains an opportunity for stakeholders to appeal decisions made regarding this project within one month or pursue legal action within two months if they feel their concerns are not being addressed adequately.