The L1 metro line in L'Hospitalet will fully reopen on August 29, ending a six-week closure for extensive track renovations. This project aims to enhance reliability and passenger comfort.
The long-awaited return of the L1 metro service in L’Hospitalet is set for August 29, following a six-week hiatus that disrupted travel between key stations. The closure, which began on July 17, was necessary for significant upgrades along the route connecting Santa Eulàlia, La Torrassa, and La Florida with Barcelona’s Mercat Nou and Plaça de Sants stations.
Transports Metropolitans de Barcelona (TMB) confirmed that the renovation work proceeded according to schedule, allowing for the replacement of approximately 2.1 kilometers of track. This included the installation of 1,580 meters of new general track and an additional 510 meters specifically for workshop areas.
The total investment for this project reached €11.5 million, aimed at enhancing infrastructure reliability and reducing operational disruptions. Key improvements include updated rail sections, drainage systems, signaling enhancements, and other essential railway components designed to minimize vibrations and improve passenger comfort.
A notable aspect of the renovation involved upgrading the expansion joints located between Santa Eulàlia and Mercat Nou. These joints are crucial as they accommodate changes in rail length due to temperature fluctuations, thereby preventing potential structural issues.
This initiative also addressed maintenance needs at the historic Santa Eulàlia workshop, where five pit tracks were renewed alongside access points and conventional catenary systems replaced with rigid ones. TMB emphasized that these enhancements will bolster safety measures while streamlining operations across this vital transit line.
The temporary closure impacted one of the busiest segments of the metro system; prior to renovations, affected stations recorded an average of 43,000 daily validations during weekdays in July and around 36,000 in August. To mitigate inconvenience during construction, TMB operated a special bus service linking Florida station with Plaça de Sants every four to nine minutes on weekdays.
TMB deployed over 170 workers, who worked around-the-clock shifts to ensure timely completion without extending disruptions beyond planned schedules. Additionally, more than 2,100 hours were dedicated to providing passenger information at key locations like Santa Eulàlia and Mercat Nou throughout the construction period.
The reopening marks a significant milestone not only for commuters but also reflects TMB’s commitment to improving public transport infrastructure across Barcelona’s metropolitan area. As services resume next week, passengers can expect a more reliable experience on one of their most frequented lines.
The full restoration of service is anticipated to enhance daily commutes significantly as residents return from summer vacations. For those planning their journeys post-reopening, regular metro schedules will resume from August 29 onwards at all affected stations.